Subcontractor Payment Schedule: A Practical Checklist for General Contractors
The subcontractor payment schedule determines when your subs get paid, how much they receive, and what documentation they must provide. Managing it poorly creates disputes, slows down project progress, and exposes you to prompt payment penalties.
This checklist and FAQ covers everything a GC needs to manage subcontractor payments correctly.
Subcontractor Payment Schedule Checklist
At Subcontract Execution
- Billing cutoff date specified in the subcontract
- Pay application format defined (AIA G702/G703 or project-specific)
- Retainage rate and reduction terms documented
- Prompt payment obligations stated (statutory and contractual)
- Lien waiver requirements specified (conditional and unconditional)
- Schedule of values submission deadline set
- Stored materials billing rights and documentation requirements clarified
- Change order billing procedures established
Monthly Processing
- All subcontractor pay applications received by the deadline
- Each pay application reviewed against field-verified completion
- Retainage calculated at the correct current rate
- Conditional lien waiver received for current billing period
- Unconditional lien waiver received for prior billing period
- Insurance certificates confirmed current
- Certified payroll received (if applicable)
- Approved amounts entered into the GC's consolidated pay application
Payment Disbursement
- Owner payment received and deposited
- Subcontractor payment amounts calculated (approved billing minus retainage)
- Payment issued within the statutory prompt payment window
- Payment confirmation sent to each subcontractor
- Payment amounts recorded in the project accounting system
Understanding Payment Timing
The subcontractor payment schedule creates a cascade that starts with the owner and ends with the sub's material suppliers.
| Event | Typical Timing | GC Responsibility |
|---|---|---|
| Sub performs work | Continuous | Monitor progress |
| Sub submits pay application | 3 days after cutoff | Review and verify |
| GC includes in owner pay app | 5-7 days after cutoff | Consolidate accurately |
| Owner certifies and pays GC | 30 days after submission | Track and follow up |
| GC pays subcontractor | 7 days after receipt | Pay promptly per statute |
The total cycle from work performed to sub payment runs 40-50 days. During this period, the subcontractor finances their labor, material, and equipment costs out of pocket.
Key Payment Terms Every GC Should Understand
Pay-when-paid. The GC's obligation to pay the sub is triggered when the GC receives payment from the owner. The sub must wait until the GC gets paid, but the GC cannot unreasonably delay payment after receipt. Most states enforce pay-when-paid clauses as creating a reasonable timing condition, not a permanent excuse for non-payment.
Pay-if-paid. The GC's obligation to pay the sub exists only if the GC receives payment from the owner. If the owner does not pay, the GC has no obligation to pay the sub. Several states (California, New York, North Carolina) have declared pay-if-paid clauses unenforceable as against public policy.
Retainage flow-through. The retainage the GC holds from subcontractors should mirror the retainage the owner holds from the GC. When the owner reduces retainage at 50% completion, the GC should reduce sub retainage correspondingly. When the owner releases retainage at close-out, the GC releases sub retainage within the prompt payment window.
Frequently Asked Questions
What is the standard payment frequency for subcontractors on commercial projects?
Monthly billing is standard on commercial construction projects. Subcontractors submit pay applications once per month based on work completed through the billing cutoff date. Some fast-track or large projects allow bi-weekly billing to improve subcontractor cash flow.
Can a GC hold subcontractor payment beyond the prompt payment deadline?
Only for documented disputes. Most state prompt payment acts allow the GC to withhold payment on disputed amounts if the GC provides written notice specifying the reason for the dispute and the amount withheld. The undisputed portion must be paid within the statutory window.
How should a GC handle a subcontractor who consistently submits late pay applications?
Document each late submission in writing. Remind the sub of the contractual submission deadline. If late submissions delay the GC's pay application to the owner, the sub may be liable for the resulting payment delay. Consider adding a late submission penalty to future subcontracts.
What documentation should a GC require with each subcontractor pay application?
Standard documentation includes: the pay application form (G702/G703), conditional lien waiver for the current billing period, unconditional lien waiver for the prior period, stored materials documentation (if applicable), certified payroll (if required), current insurance certificates, and change order backup for any new change order billing.
How does the subcontractor payment schedule change during project close-out?
Close-out payments are conditioned on additional requirements: punch list completion, warranty delivery, O&M manual submission, as-built drawings, training records, and final unconditional lien waivers. The GC should start tracking these requirements at 75% completion so they do not delay final payment.
What are the penalties for late subcontractor payment?
Penalties vary by state. Most state prompt payment acts impose interest on late payments, typically at 1-2% per month. Some states allow the subcontractor to recover attorney's fees in addition to interest. Federal projects under the Miller Act require prompt payment within 7 days of receipt and impose interest at the rate specified in the subcontract or prime contract.
Streamline Subcontractor Payments
Managing payment schedules across 15-20 subcontractors requires accurate tracking of deadlines, retainage, and documentation. SubcontractorAudit automates the payment workflow so every sub gets paid correctly and on time.
See how it works -- Request a pay app audit
<!-- standardized-cta-v1 -->Ready to connect your money layer? SubcontractorAudit links GCs, subcontractors, owners, and lenders on every construction project — one platform for every dollar and document. Book a demo or see the platform in action.
<!-- positioning-v2 -->
About SubcontractorAudit
SubcontractorAudit is the Procore for the money layer — the financial nervous system connecting general contractors, subcontractors, owners, and lenders on every construction project. We automate the document, dollar, and compliance flows that move between every party on a jobsite, so money moves faster and nothing falls through the cracks.
Founder & CEO
Founder and CEO of SubcontractorAudit. Building the financial nervous system for construction — the platform that connects general contractors, subcontractors, owners, and lenders on every project.