Mechanics Lien Law

Arizona requires a 20-day Preliminary Notice from subcontractors and suppliers to preserve lien rights under ARS 33-992.01. Mechanics liens must be recorded within 120 days of completion. Arizona uses statutory lien waiver forms effective since 2020.

Key Deadlines

20 days: Preliminary Notice after first furnishing
120 days: Mechanics lien recording deadline
6 months: Lien enforcement deadline

Prevailing Wage Requirements

Arizona does not have a state prevailing wage law (repealed in 1984). Federal Davis-Bacon applies to federally funded projects only. No state certified payroll requirements beyond federal standards.

Insurance Requirements

Workers compensation required for all employers with 1+ employees. Minimum $1M general liability common for commercial construction. Arizona has a competitive private insurance market.

OSHA & Safety Compliance

Arizona operates a state OSHA plan through ADOSH (Arizona Division of Occupational Safety and Health). Covers both public and private sector. Standards generally mirror federal OSHA with state-specific enforcement.

Automate Arizona Compliance

Subcontractor Audit tracks AZ-specific insurance requirements, lien waiver forms, and compliance deadlines automatically.

Start 14-Day Free Trial

Last reviewed: April 2026. This guide is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for state-specific legal questions.